theRidge.png Great water quality is just one of the benefits of living on the ridge. If you're new to Paradise, visit the WelcometoTheRidge website to learn about all the other great things happening in our community.

 

  


ZONEA

Project Description

This grant (applied for before the Camp Fire) was awarded in September 2022, for a new generator at the WTP, plus pipeline and pump station upgrades for Zone A. The upgrades provide for redundancy in bringing water to town from the treatment plant. This is also known as the ZAPS Project.  

 

Estimated Spending Plan

 Project Phase  Fiscal Year 22/23  Fiscal Year 23/24  Fiscal Year 24/25 Total
 Design / Management $258,563 300,000 66,752 $625,315
 Construction $1,685,415 $2,500,000 $2,073,900 $6,259,315
 Total $1,943,978 $2,800,000 $2,140,652 $6,884,630

Project Manager

  • Blaine Allen - District Engineer / Water Works Engineering - Sheila Nilsen
    Department: Water Treatment

Funding Source

Project Status

construction icon Construction

PID's board considered these alternatives:

The Board discussed several alternative locations for the redundant pipeline during the grant application phase. Ultimately, it was decided the best route for the pipeline was to follow Skyway.

 

Benefits to PID and its Customers

A secondary distribution main will be installed so that there are two distribution mains serving the District. This will allow for one to be put offline if necessary for any repairs or maintenance that may need to be completed.

Anticipated Project Timeline

 concept3
Concept Approval
planning icon
Planning
design icon
Design
construction icon
Construction
completed icon
Completion
July 2017 Jan. 2017 - March 2017 April 2017 - Dec. 2017 April 2023 - Dec 2024 Dec 2024
 

 

 

 

 

 

Project details updated February 2024

Was this article helpful?

We are always looking for ways we can improve our services. If you need additional help please contact customer service.

If you'd like to give us some feedback on this article or the website click here.