Project Description
Replace the damaged culvert at Henson Road. The project includes hazard mitigation efforts to replace the previously plastic culvert with metal for greater resiliency to future fire-related events.
Spending Plan
| Project Phase | Prior Years | Fiscal Year 2023 to 2024 | Fiscal Year 2024 to 2025 | Fiscal Year 2025 to 2026 | Total |
|---|
| Design / Management | N/A | $5,000 | $10,000 | $5,000 | $90,009 |
| Construction | N/A | $0 | $0 | $134,173 | $134,173 |
| Total | N/A | $10,000 | $10,000 | $139,173 | $224,182 |
Project Details
- Project Manager: Blaine Allen, District Engineer, and Water Works Engineering
- Funding Source: FEMA Disaster Recovery Funds, CalOES, PID
- Project Status: Design Phase
Anticipated Project Timeline
- Concept Approval: July 2017
- Planning: July 2017 to March 2026
- Design: May 2024 to March 2026
- Construction: 2026
- Completion: 2026
Benefits to PID & Its Customers
Replacement of culvert that was damaged during the Camp Fire and repair the roadway to provide exit to residents.