Zone A ImprovementsProject Description

This grant (applied for before the Camp Fire) was awarded in September 2022, for a new generator at the WTP, plus pipeline and pump station upgrades for Zone A. The upgrades provide for redundancy in bringing water to town from the treatment plant. This is also known as the ZAPS Project.

Spending Plan

Project PhaseFiscal Year 2022 to 2023Fiscal Year 2023 to 2024Fiscal Year 2024 to 2025Total
Design / Management$258,563$300,000$66,752$625,315
Construction$1,685,415$2,500,000$2,073,900$6,259,315
Total$1,943,978$2,800,000$2,140,652$6,884,630


Project Details

  • Project Manager: Blaine Allen, District Engineer and Water Works Engineering 
  • Funding Source: FEMA Hazard Mitigation Grant / Operating Fund
  • Project Status: Complete 

Anticipated Project Timeline

  1. Concept Approval: Complete 
  2. Planning: Complete 
  3. Design: Complete
  4. Construction: Complete 
  5. Completion: November 2025

Benefits to PID & Its Customers

A secondary distribution main will be installed so that there are two distribution mains serving the District. This will allow for one to be put offline if necessary for any repairs or maintenance that may need to be completed.