Rehabilitation of storage tanks c, d, and e 

Storage Tank RehabProject Description

PID’s maintenance schedule calls for rehabilitating three of the District's water storage tanks, C, D and E. 

In December 2017, consultants completed a condition assessment to rank the maintenance priority of each tank. The Board of Directors shall consider funding one tank rehab per year, starting with the tank in the worst condition.

Spending Plan

Project PhasePrevious Fiscal Year ExpensesFiscal Year 2023 to 2024Fiscal Year 2024 to 2025Total
Design / Management$60,000$190,000$700,000$950,000
ConstructionN/AN/A$3,500,000$4,170,000
Total$60,000$190,000$4,200,000$5,120,000


Project Details

  • Project Manager: Bill Taylor, Assistant Engineer
  • Funding Source: Operating Fund
  • Project Status: Construction

Anticipated Project Timeline

  1. Concept Approval: December 2017
  2. Planning: 2018 to 2024
  3. Design: 2024
  4. Construction: 2025 - December 2026
  5. Completion: To Be Determined

Benefits to PID & Its Customers

  • PID’s storage tanks will continue to function well and their useful life will be extended