Mainline Replacement

Mainline ReplacementProject Description

This is a two phase project, likely continuing until a decade (until 2034). This project is designed to replace and repair the water distribution main pipelines and related appurtenances that were damaged and/or contaminated as a result of the 2018 Camp Fire. This includes replacement and/or repairs of 79,466 LF of water main pipe and service laterals based on initial sampling results and damage assessments performed to date. The project also includes repair of additional leaks resulting from the 2018 Camp Fire and costs relating to project/construction management. Mainline repair is expected to begin Fiscal Year 2023 to 2024 and is expected to be completed over a 10-year time frame.

Project Info for All Two Phases From the Original FEMA Assessment

  • Main Line Replacement: $29,543,360
  • Estimated Leak Repair: $31,760,578

Mainlines in Phase 1 of This Project

Portions of:

  • Xeno
  • Judy
  • Gracephil
  • Scandia
  • Farber
  • Linry
  • Cypress
  • Clark Road
  • Crandall
  • Deodara
  • Himmel
  • Forest
  • York Towne
  • Paradise Avenue
  • Moon-Hazel
  • Fawndale
  • Sawmill
  • Feather River Place
  • Skyway
  • Pacific-Orchard
  • Coral Avenue / Coral Circle
  • Bella Vista-Del Monte
  • Aspen
  • Lowry
  • Graystone
  • Kemlyn
  • Woodsdale

View Mains Replacement Project Drawings (PDF).

Spending Plan

Project PhasePrior YearsFiscal Year 2023 to 2024Fiscal Year 2024 to 2025Fiscal Year 2025 to 2026Total
Design / ManagementN/A$399,730$889,448$600,000$1,889,178
ConstructionN/A$0$8,894,4846,000,000$24,478,795.89
TotalN/A$399,730$9,783,932$6,600,000$26,367,973.89

Project Details

  • Project Manager: Blaine Allen, District Engineer, and Water Works Engineering
  • Funding Source: FEMA Disaster Recovery Funds / Insurance / CalOES, PID Operating Fund, California State Water Resources Board (DWSRF)
  • Project Status: Construction

Anticipated Project Timeline

  1. Concept Approval: Complete
  2. Planning: Complete
  3. Design: Phase 1 Complete. Phase 2 2025 to 2026. 
  4. Construction: Phase 1 March 2024 to June 2026. Phase 2 2027 to 2028.
  5. Completion: Phase 1 June 2026. Phase 2 December 2028. 

Benefits to PID & Its Customers

Restoration of pipelines damaged during the 2018 Camp Fire. The project includes backflow prevention as mitigation to prevent future damage from wildfires. Replacement of these mains will provide better flows, newer infrastructure, and longevity to the system.