Project Description

Post-Camp Fire Pipeline Recovery

 

Spending Plan

 Project Phase Previous Fiscal Year Expenses  Fiscal Year 15/16  Fiscal Year 16/17  Fiscal Year 17/18  Fiscal Year 18/19  Fiscal Year 19/20 Total
 Planning  -  -  -  -  -   -  -
 Design  -  -  -   -  -  -  -
 Construction  -   -  $405,000 -  -   -  $405,000
 Total - - $405,000 - - - $405,000

Project Manager

Funding Source

Project Status

  •  Complete

Budgeted vs. Actual Costs

planning icon
Budgeted Expenses
completed icon
Actual Expenses
$405,000 $369,000

 

 

Project Timelines

Street / Area Number affected lots  concept3
Damage Assessment

Planning

Design

Construction

Completion
Paige Lane 2 Pending Sept. 2016 - March 2017 Sept. 2016 - March 2017 May 2017 - Sept. 2017 Sept. 2017
Mulberry Street 7 In Process        
             
 
 

Project Photos

Slider

Project details updated November 2017