Project Description

The primary objective of the project is to replace the aging infrastructure and provide necessary redundancy to the District’s water treatment plant.  We will be replacing our existing equalizer tank with one bifurcated cast-in-place concrete tank, giving the treatment plant the ability to take a portion of the tank out of service for any cleaning or repairs and continue plant functions, such as backwashing filters and flushing clarifiers without interruption. Replacement of existing tank that needs repair/replacement. Replace a single tank with two tanks which will facilitate a possible higher capacity at the water treatment plant. Allow for the cleaning and maintenance of the tanks as one can be put offline while this work is completed.

 
 

Spending Plan Estimates

 Project Phase  Prior Years  Fiscal Year 23/24  Fiscal Year 24/25 Fiscal Year 25/26 Total
 Design / Management  -  $236,929 tbd tbd tbd
 Construction  -  $0 tbd tbd tbd
 Total - $236,929 tbd tbd tbd

Benefits to PID and its Customers

Replacement of existing tank in need of repair/replacement. Replace a single tank with two tanks which will facilitate a possible higher capacity at the water treatment plant. Allow for the cleaning and maintenance of the tanks as one can be put offline while this work is completed.

Anticipated Project Timeline

 concept3
Concept Approval
planning icon
Planning
design icon
Design
construction icon
Construction
completed icon
Completion
Complete Complete Feb 2024 June 2024-June 2025 2025

 

Project Info

 

 

Project details updated March 2024

 

Was this article helpful?

We are always looking for ways we can improve our services. If you need additional help please contact customer service.

If you'd like to give us some feedback on this article or the website click here.