Project Description
This grant (applied for before the Camp Fire) was awarded in September 2022, for a new generator at the WTP, plus pipeline and pump station upgrades for Zone A. The upgrades provide for redundancy in bringing water to town from the treatment plant. This is also known as the ZAPS Project.
Estimated Spending Plan
Project Phase | Fiscal Year 22/23 | Fiscal Year 23/24 | Fiscal Year 24/25 | Total |
Design / Management | $258,563 | 300,000 | 66,752 | $625,315 |
Construction | $1,685,415 | $2,500,000 | $2,073,900 | $6,259,315 |
Total | $1,943,978 | $2,800,000 | $2,140,652 | $6,884,630 |
Project Manager
- Blaine Allen - District Engineer / Water Works Engineering - Sheila Nilsen
Department: Water Treatment
Funding Source
- FEMA Hazard Mitigation Grant / Operating Fund
Project Status
Construction
PID's board considered these alternatives:
The Board discussed several alternative locations for the redundant pipeline during the grant application phase. Ultimately, it was decided the best route for the pipeline was to follow Skyway.
Benefits to PID and its Customers
A secondary distribution main will be installed so that there are two distribution mains serving the District. This will allow for one to be put offline if necessary for any repairs or maintenance that may need to be completed.
Anticipated Project Timeline
Concept Approval |
Planning |
Design |
Construction |
Completion |
July 2017 | Jan. 2017 - March 2017 | April 2017 - Dec. 2017 | April 2023 - Dec 2024 | Dec 2024 |
Project details updated February 2024