Project Description
The primary objective of the project is to replace the aging infrastructure and provide necessary redundancy to the District’s water treatment plant. We will be replacing our existing equalizer tank with one bifurcated cast-in-place concrete tank, giving the treatment plant the ability to take a portion of the tank out of service for any cleaning or repairs and continue plant functions, such as backwashing filters and flushing clarifiers without interruption. Replacement of existing tank that needs repair/replacement. Replace a single tank with two tanks which will facilitate a possible higher capacity at the water treatment plant. Allow for the cleaning and maintenance of the tanks as one can be put offline while this work is completed.
Spending Plan Estimates
Project Phase | Prior Years | Fiscal Year 23/24 | Fiscal Year 24/25 | Fiscal Year 25/26 | Total |
Design / Management | - | $236,929 | tbd | tbd | tbd |
Construction | - | $0 | tbd | tbd | tbd |
Total | - | $236,929 | tbd | tbd | tbd |
Benefits to PID and its Customers
Replacement of existing tank in need of repair/replacement. Replace a single tank with two tanks which will facilitate a possible higher capacity at the water treatment plant. Allow for the cleaning and maintenance of the tanks as one can be put offline while this work is completed.
Anticipated Project Timeline
Concept Approval |
Planning |
Design |
Construction |
Completion |
Complete | Complete | Feb 2024 | June 2024-June 2025 | 2025 |
Project Info
Project details updated March 2024